Container House – Hainan concentrated medical observation and isolation modular house hospital

Project Overview

Project Name: Hainan concentrated medical observation and isolation modular house hospital project

Project contractor:GS Housing group

Project QTY: 902 sets prefab porta cabins

Construction time: August 18, 2022

Project cycle: 7 days

Project area: 154066.96

porta cabin (3)
porta cabin (4)

Advantages of GS housing prefab porta cabins

1. Fast shipping

When received the task, we overcame the difficulties of traffic control and material shortage during the epidemic prevention and control period, quickly assembled transportation vehicles, and successively shipped prefab container houses from Guangdong and Jiangsu prefabricated house production base to Zhanjiang, under the coordination and cooperation of various departments.

2.Heavy workload

During the construction period, the project team quickly formulated a plan, optimized the construction process, formed a construction team to fight on the front line of construction, raced against time, went all out to fight the epidemic, strived for early delivery, and built a new "moat" for epidemic prevention in Hainan.

3.Fast installation

The installation of the two building must be completed within one day,the on-site construction supervisor quickly mobilized 70 workers to enter the site for construction, ensuring the smooth completion of the task.

4.Nucleic acid testing in heavy rain

Despite the heavy rain, the project construction personnel still voluntarily queued up to accept the nucleic acid test; each person should receive two masks every day, and nucleic acid should be done at a fixed time every day to ensure peoples safety during the outbreak

Porta cabin
porta cabin (5)

5.Construction in the rain

In order to ensure the construction progress, under the premise of ensuring personal safety and product quality, the builders of GS Housing follow the principle of "do quickly in light rain", "stop in the heavy rain", and " grasp time to ensure progress".  fortunately the construction process didnt affect due to the water level problem.

6.Full cooperation

All the staff stuck to their posts, carefully sorted out the plan, and kept a tight grip on the production schedule. They were still discussing construction problems at more than 3 a.m. They did not delay or slack off, and went all out to ensure the completion of the project on schedule and with high quality

7.Work day and night

The builders stayed up late to catch up with the construction schedule, sometimes sleeping with their clothes on, and everyone did their best to push the construction speed.

Walking tens of thousands of steps in half a day has long been the norm for everyone. On the construction site, every corner of the building flashed the figures of GS Housing builders with all their strength.

Porta cabin
Porta cabin

Although Hainan pressed the "slow button" because of the epidemic, the builders of GS housing ran out of "acceleration". We will speed up the project with our best efforts and the fastest speed, strive to complete the task with quality and quantity, and make our due contribution to the comprehensive victory of epidemic prevention and control in Hainan!

porta cabin (2)
porta cabin (1)

Post time: 04-11-22